An example of an estimate for building a house: the principle of calculating the costs of materials and construction and installation work


Even a short grocery shopping trip requires a preliminary list that will help you purchase everything you need at once and navigate the size of your upcoming investment. What can we say about construction, because you can’t bring materials for it in a bag, you also have to take into account transportation costs. That is why during the design process, in addition to architectural and construction documentation, an estimate for the construction of a house made of aerated concrete is also developed. This is exactly what we will talk about in this article.

Types of construction estimates, the purpose of their preparation

When performing estimate calculations for large construction projects, they are guided by existing standards: territorial, industry, federal (if financed from the state budget). There are state standards for the implementation of estimates (GSN), which are used by design institutes. There are also individual (company) standards: they are developed by a certain organization, which itself is engaged in construction.

There is nothing particularly new in these standards, since they are in any case based on territorial or federal directories. All these collections constitute a unified system of rationing and pricing in Russian construction. To take into account the inflationary rise in prices of materials and the features of new technologies, the information in them is periodically updated.

Vitaly Kudryashov

Builder Author of the portal full-houses.ru

Ask a Question

The larger the project, the longer it takes to build, and the more difficult it is to determine its estimated cost due to inflation. After all, in addition to materials, prices also change for everything else: equipment, energy, costs for renting special equipment, and wages for workers increase.

To get out of this situation, several estimates can be drawn up for the same object.

Local

In this estimate, the costs of one type of work or stage of construction are calculated, taking into account the volume, standardized quantity and prices of materials, inventory and equipment necessary to complete it.

  • Let’s say an estimate is being drawn up for a 10x10 aerated concrete house, in which direct and overhead costs are localized only taking into account the construction of the box. The data in it is grouped into sections according to the required construction sequence and by type of work. As a rule, these are: earthworks; foundation formation; walls and partitions; ceilings and staircases; roof.
  • The materials required for their construction (not only quantities, but also prices) can be indicated in a separate resource sheet, or included in the general estimate. If the costs of using equipment are not included in overhead costs, then the time and cost of its use are also included in the local estimate.
  • The costs of work in the estimate can be displayed in two categories of prices: current (existing at the time of drawing up the estimate) and basic (with a projected increase in price).
  • When determining the estimated cost of an object, the presence of complicating factors must be taken into account: carrying out work near power lines, in cramped conditions (for example, near existing buildings or communications), on a mountain slope. These factors are taken into account by using the coefficients given in the reference books.
  • Local estimate is the simplest type of financial and construction documentation. It consists of two interconnected parts: the first is a list of works with a code, their unit of measurement and costs of implementation; to the second list of materials with prices and total amounts for their purchase.

Vitaly Kudryashov

Builder Author of the portal full-houses.ru

Ask a Question

The essence of the local estimate is to detail technological operations and determine the scope of work. As for the costs, at the time of drawing up the document they have not yet been finalized and adjustments are possible.

Local estimates can be prepared not only for general construction or engineering work, but also for special types of work - the construction of a drinking well, for example, or the installation of forced ventilation. The initial data, according to which the scope of work is determined, are drawings and diagrams of components, specifications of equipment and tariffs for its rental.

Overhead costs represent a certain percentage of the amount of direct costs, and are accrued either for each section separately or according to the estimate as a whole.

Object

An object estimate is a general financial document for the construction of an object, into which all local costs are summarized and summarized. That is, it is compiled on the basis of pre-developed local estimates, and can combine not only the work on the construction of the building itself, but also, for example, landscaping the garden area.

This also includes costs that, not having a direct relationship directly to the construction process, are classified as other. This could be renting a cabin for workers, or an increase in the cost of monolithic work during the winter season. For small facilities, such an estimate may not be carried out. In this case, the limited costs that we just talked about are included in the calculation, which plays the role of a local estimate.

Summary

The summary estimate differs from the object estimate in that it does not include limited costs. It is also compiled according to a certain form and represents the sum of local estimates compiled at two price levels.

The consolidated estimate compiled for residential buildings and social and cultural facilities includes 9 chapters into which funds are distributed. These include:

  1. Preparing the area for construction or major repairs.
  2. Construction of main facilities.
  3. Construction of secondary objects.
  4. External engineering networks.
  5. Landscaping and landscaping.
  6. Temporary structures.
  7. Other expenses.
  8. Technical supervision of construction.
  9. Survey work and design.

The estimate is accompanied by an explanatory note containing all the main parameters of the object. If several contractors are involved in construction, a separate statement of work performed and costs is drawn up for each of them.

Most often, the stumbling block between the customer and the contractor is the cost of work. On large projects, where any customer has his own capital construction department with a full set of specialists, he can submit his own version of the estimate. The document is drawn up on the basis of data gleaned from the project, and is called a project estimate.

The contractor, for its part, provides its estimate (it is called “contractual”), which will take into account the costs of subcontracting work and determine the projected profit. The two estimates are compared, disagreements are discussed, and this makes it possible to come to a solution that suits both parties.

By the time construction is completed, the contractor draws up another estimate - an executive estimate, which takes into account all the funds actually spent. This document, which presents tables detailing the work performed, the materials used and their cost, is fundamental for calculating the book value of the object when it is put into operation.

If the executive estimated cost exceeds the previously agreed amounts, the customer may not agree to pay extra. In this case, he has the right to involve independent experts to assess the value of the object. But considering that you will also have to pay for the examination - and not at a fee, but half a percent of the estimated cost, it may still be cheaper to meet the contractor halfway.

Preparation of the land plot

Purchasing a plot of land is a rather complicated procedure for an unprepared person. But only after going through the entire process of registration, receiving a certificate of ownership, cadastral number, permission to use the site for individual housing construction, can you begin to build a house.

You should not start by leveling the surface of the site or cutting down trees for the construction site of the house. A house begins with a project, and a specialist designer always takes into account in his work such subtleties as the terrain or the preservation of trees and shrubs. And, most likely, construction and even preparatory work before the development of a construction project will turn out to be wasted costs.


The terrain of the site quite strongly influences the cost of preparatory work. Source stroytehnika.su

How to make an estimate - popular techniques

An estimate developed by a professional for the construction of a house made of aerated concrete (10x10 2 floors, or any other) will allow you to achieve the correct and most efficient use of the budget. There are several methods by which calculations can be made. Some of them are used to calculate large objects, others are more applicable for individual construction.

Analog

The name speaks for itself. The calculation of one object can be made on the basis of a previously constructed another, with a similar design (similar). This technique is used precisely by organizations that build turnkey houses that differ only in plan size or architectural style of the facade. At the same time, the estimate for a house made of aerated concrete is 100 sq. m., in the structural part it may well be formed according to the estimate of a house of 150 sq. m. Only the volume of work is adjusted, and the final price per square meter of living space will be the same.

Time-based

This technique is used less frequently, since it is based not on the volume of work, but on the cost of a certain amount of time spent on their implementation. It is applicable in cases where the amount of work as a whole is small, but it takes a lot of time to complete it. Accordingly, the estimate is made not for the object or its part, but for a certain type of work, often special. For example, when designing a facade or interior, a panel using the sgraffito technique or stucco on the ceiling can be made according to this estimate.

Basis-index

The calculation basis in this method is based on basic prices from federal or territorial directories approved back in 2000, and recalculated to current prices using a system of coefficients (indices). This makes it possible to take into account the factor of inflationary rise in construction costs both in general according to the estimate and for individual types of work.

For small objects, indexes can also be used at the end of sections of local estimates. Alternatively, according to the certificates of completed work, direct costs are calculated (taking into account the coefficient for cramped conditions), and the inflation index is applied to this amount.

Basic compensation

When using the basic-compensation method, the estimate is based on basic prices (in current prices), and expenses incurred during construction due to price increases are compensated by the customer upon completion of the work. In addition to the increased cost of materials, the list of costs to be paid includes increased electricity tariffs, temporary losses, and reduced labor productivity, which do not depend on the contractor.

The described method very accurately reflects the state of affairs at the construction site, therefore the estimate for the construction of a turnkey aerated concrete house (6x20, 13x13, 7x8 or other size) is most often drawn up precisely on the principle of compensation in relation to the base tariffs. But there are other ways to determine real prices for materials and work, which designers most often use in the process of cooperation with private customers.

Labor cost estimate

This type of estimate is used mainly when the estimate is made not for an object, but for a certain type of work - for example, for installing a foundation or laying walls. The contractor determines the optimal cost of 1 m2 or 1 m3, and based on this figure, calculates the total amount. True, it does not include overhead or transportation costs, and the customer will have to compensate for them separately.

It is difficult to determine how much this will cost for large volumes of work, so this method is used mainly by private teams that do not have their own transport base. The owner pays the costs of delivery of materials himself, as they arrive at the construction site.

Universal estimate

There is such a thing as the universality of estimates compiled on aggregated indicators. This document, which is also drawn up by the contractor, lists all the technological stages of construction, but without detailed details of the work. Simply, the estimate is accompanied by an explanation of the materials reflecting their prices and total amounts. On the part of the customer, only an analysis of the estimate is carried out with control of the volume of work according to the project, as well as a comparison of prices, for example, those offered by competing contractors. By agreement of the parties, the price level can be adjusted.

Detailed estimate

Unlike the universal version, the detailed estimate contains all the necessary data that allows you to see all the names of the works and their technological sequence. This may well be an estimate for a 100 sq. m aerated concrete house. Its normative part is usually based on the contractor’s technical conditions and calculations, including those taking into account the technologies he uses in construction.

Any serious company has its own documentary base, and many even draw up technological maps for this or that type of work on their own. A distinctive feature of a detailed estimate is the allocation of the full amount of costs for each stage of construction, which allows the customer to pay for the work actually completed. The document is simple in form and understandable to anyone - there are prospects behind this technique, and it can be used not only on small objects.

Construction of the “box”

The “box” is usually understood as the frame of a building without additional insulation, finishing, wiring and pipes. The cost of its construction depends on the chosen material:

  • The cheapest option is to build a frame or frame-panel type house - from 11,000 rubles/m2;
  • Construction of a “box” of a wooden house will cost from 13,000 rubles/m2;
  • The construction of a house frame from foam concrete will cost from 14,000 rubles/m2;
  • Buildings using the Izodom technology are offered from 15,000 rubles/m2;
  • To build a brick wall frame will cost at least 18,000 rubles/m2.

Now we multiply this price by the estimated area. Thus, the cost of constructing a “box” of a country house or cottage with an area of ​​100 m2 will average 1.5 - 2 million rubles.

We will look at the features of these materials in more detail at the end of this article.

Estimate for the construction of a house made of aerated concrete 10x10 - how to draw it up correctly

To draw up an estimate, you need initial data (they can only be gleaned from the project), according to which the volume of work and selection of materials will be determined.

Let's present an approximate data table for an estimate for a 10 by 10 house made of aerated concrete (box):

Necessary informationData for estimates for a one-story aerated concrete house
Wall materialAerated concrete
Wall height including ceiling3m
Wall thickness0.4 m
Number of storeys1
AtticNo
Length and width of the house in plan10*10 m
Foundation typeMonolithic reinforced concrete slab
Foundation slab thickness0.25 m
Floor typeOn beams 100*180, in increments of 500 mm
ArmopoyasNo
Roof structure/covering2-pitch/soft tiles
Overhang length/roof angle500mm/45 degrees
DrainpipesPVC
Wall insulationSlab extruded polystyrene foam
Insulation thickness100 mm
Wall perimeter35 m
WindowNo
DoorsNo
Facade finishingNo
Interior decorationNo
PartitionsNo

If you prepare an estimate for a house made of aerated concrete yourself, it is better to calculate each stage of construction separately. This is convenient if different contractors will be hired for the work, or you plan to do some of it yourself (for example, laying walls).

Preparatory work and laying the foundation

To get a detailed estimate for a house made of aerated concrete, it is necessary to detail all the processes and identify the materials used in them. Let us present to your attention a list of work that precedes construction and is carried out when laying a slab foundation at the lowest possible level of foundation - when there is only a bulk cushion in the ground, and the slab itself is located on the surface.


p/p
List of construction and installation work and necessary materials Unit

change

QuantityMaterialsWorks
PriceSumPriceSum
1Ground leveling and geodetic workM2100
2Excavation work with soil removalM340
3Construction of a cushion made of a mixture of sand and gravelM2135
4PGSM330
5Pouring a sub-concrete slab (100 mm)M2100
6Lean concrete (class B7.5)M311
7Installation of embedded partsset1
8Set of embedded partsset1
9Formation of the main slab with installation of a frame made of reinforcement barsM2100
10Fittings A III (D14)tn1,53
11Fittings A III (D12)tn1,17
12Annealed wire d=1.2mmkg18
13LumberM30,59
14Heavy concrete for the main slab (class B22.5)M339
15Concrete pump rentalchange1
16Slab waterproofing (coating) Penetron Admixkg159
17Polyethylene film 100 micronsM2182
18Assembling inventory formwork panelsM2
19Rental of inventory formworkset1
20Sealing seamskg30
21Penebar harness for seam waterproofingM.P.46
22Assembling the frame for the plinthM36,7
23Concrete pump rentalchange1
24Concrete M22.5 for pouring the baseM35,85
25Reinforcement A III (D8 mm)tn0,092
26Reinforcement A III (D12 mm)tn0,077
27Annealed wire d=1.2mmkg13,5
28Dismantling of formworkM240
29Backfilling of soil around the perimeter of the pitM318,5
30Truck crane operationchange1
31Consumables and hardware

The table shows a list of work performed during the construction of a slab using rigid concrete preparation. This is a classic technology, but today, when constructing shallow slabs, the concrete base is often replaced with a PVC membrane. In this case, instead of lean concrete used for preparatory concreting and coating or roofing felt waterproofing, a layer of membrane will be present in the slab cake.

We did not put prices in the estimate - they differ greatly in the regions, so there is no point in making calculations. Enter them yourself, focusing on the prices of local contractors, and by multiplying and summing, you will get an approximate estimate for zero-cycle work.

If we add another column to the table we propose, it will be possible to enter the actual amounts spent, including unexpected ones.

The simplest layout

The layout is extremely simple. In this case, the kitchen is separated from the room.

Sometimes an architect will draw a gorgeous layout, everything is functional, bright corridors, large rooms, a huge number of windows. It is very difficult to do this from the point of view of engineering solutions because large spans are always powerful floor structures, this is an unnecessary increase in cost.

In this project everything is different: it’s simple, cheap and can be built by almost any builder with minimal qualifications.

We have a vestibule that cuts off cold air when entering the house from the street. He's the hallway. It contains a wardrobe which is a wardrobe.

Then we find ourselves in a corridor from which we can go into a room with a kitchen and a combined bathroom.

The design solutions used in this house are the simplest and most affordable.

Estimate for laying walls made of aerated concrete blocks and installing floors

Here's what the list of work on the construction of walls covered with wooden beams will look like:


p/p
List of construction and installation work and necessary materialsUnit
change
QuantityMaterialsWorks
PriceSumPriceSum
1External walls 400mm thick made of aerated blocks:
1.1Leveling the base and installing cut-off waterproofingM. p.40
1.2Ruberoidrolls6
1.3Wall masonryM3104,5
1.4Gas block 600*250*400 mm D500M3104,5
1.5Cement-based adhesive in bagskg3020
1.6Formation of window and door openingsM. p.34
1.7U-blocks for covering openings 600*250*400 mmPC50
1.8Jumper fittings A III (d12)tn0,175
1.9Wire rod AI (d1,2)tn0,03
1.10Concrete B15M31,27
1.11DSP M200 for leveling the basekg590
1.12Basalt mesh for masonry reinforcementPC60
1.13Installation of jumpers in openingsPC5
1.14Arrangement of reinforced joint for supporting raftersM. p.100
1.15Truck cranechange2
1.16Hardware and consumables
2Installation of ceilings on beams:
2.1Logs 100*180 mmM312
2.2Block 40*40 mm (cranial)M32,2
2.3Plywood thick. 5 mm M2215
2.4OSB board thickness. 9 mm M2100
2.5Fastenersset1
2.6Construction of a wooden subfloorM2100
2.7Ceiling liningM2100
2.8Laying insulationM2100
2.9Mineral wool thickness 100 mmM310
2.10Installation of vapor barrier layerM2100
2.11Roll vapor barrierM2100

Creating a roof

Now let's look at the stages of building a gable roof covered with bitumen shingles:


p/p
List of construction and installation work and necessary materialsUnit
change
QuantityMaterialsWorks
PriceSumPriceSum
1Waterproofing the edge of the wall and installing the MauerlatM. p40
2Gidroizolrolls5
3Beam with a section of 100*100 mmM30,5
4Impregnation of wood with fire retardantM2160
5Fire-retardant composition for primingl100
6Assembling the rafter systemM. p.160
7Board 50x200 mmM33,1
8Board 50x150 mmM32,3
9Board 50x100 mmM32,7
10Bar 150x150 mmM30,95
11Installation of flooring under the covering with waterproofingM2160
12Waterproofing membraneM2250
13Bar 50x50 mmM31,54
14Bar 50x100 mmM32,55
15Installation of roofing and ridge installationM2160
16Soft tilesM2200
17Ridge elements 2mPC5
18Truck cranechange1
19Hardware and consumables

Foundation - slab

The foundation of this house is a monolithic slab. It is also a subfloor. The slab is suitable for almost all soils. Tape will be cheaper. But without knowing the soil, it is dangerous to make a strip foundation.

The slab is made according to all the rules: we remove the plant layer of soil, make geotextiles, make a sand cushion. Next comes the insulation, 2 reinforcement meshes. A double mesh of reinforcement is required and nothing else.

I am an opponent of such slabs when they make widening in places of load-bearing walls, and where you have a floor, a slab with single reinforcement is usually poured 10 centimeters thick. The way the stove works is not exactly how I like it.

In terms of savings, there is none. Where you decrease the height of the concrete slab, you increase the height of the insulation. Penoplex currently costs 4,200 rubles per cubic meter. Concrete with delivery currently costs 4,200 rubles per cubic meter. I don't see any savings. If the conversation is about how this creates a larger layer of insulation, therefore warmer, I will not agree here. If we carry out thermal insulation correctly, then we insulate the entire blind area and insulate the perimeter of the house. It doesn't make any sense in this house.

Is it possible to save money on building a house?

It is unlikely that even those people who do not have any special problems with financial support will refuse reasonable savings - what can we say about developers with a limited budget. Therefore, tips that will help reduce unnecessary expenses to a minimum will be useful to both.

  • Any construction begins with the selection of a site, and its location can entail unexpected costs. Even two plots of identical size, located within the same village or dacha cooperative, can create completely different conditions for construction. One, for example, will be at a higher point, where the soil will be dry and dense - and the other will be in a lowland, and water will stagnate in it after rains.

A geological defect does not affect the price of land in any way, but its elimination may entail considerable expenses. Therefore, if you have a choice, give preference to a site at a higher location; with a minimum of terrain changes; with the ability to organize a convenient check-in. The most inconvenient areas can still be sold at a discount. In this case, in order to assess the upcoming costs of planning the site, it makes sense to make a preliminary estimate for the preparatory work.

  • In cottage villages, the price of land often includes the ability to quickly connect to centralized communications (electricity, gas, water supply and disposal). Try to find out exactly which highways run through a populated area or a specific street, and evaluate the chances of them being connected to the house. On land that is not provided with communications, the cost of landscaping work is always higher.
  • Decide in advance how actively you personally intend to participate in construction. The “do-it-yourself” option is cheap only on paper; unskilled work will create problems, if not during the construction process, then during the operation of the house. Ordering turnkey construction is attractive, but the price of the house doubles. A golden mean is possible: you could build aerated concrete walls yourself, install windows and doors, and do the finishing. It's always best to leave the foundation and roof to the professionals.

    Having a normal project and detailed estimates for all stages of work will allow you to “stay on top of things” and adequately handle numbers when concluding contracts with contractors.

  • Individual design is more expensive than standard design, but you can immediately provide for everything you need, and in the way required by the conditions of the construction site. You have to pay extra for any alterations made to a standard project, so it remains to be seen which option will be more profitable.

Vitaly Kudryashov

Builder Author of the portal full-houses.ru

Ask a Question

Do not neglect the preliminary design, because at this stage any amendments can be made free of charge. After detailed design has been completed, any rework becomes subject to a fee. And of course, the costs will be much higher if alterations have to be made during the construction process.

  • There are situations when saving is inappropriate. The category of such work includes geological surveys on the site, which provide a complete picture of the composition, mobility and strength characteristics of the soil, and the water level. Only the results of the research will make it possible to make a correct calculation of the foundation. Not only gas-block masonry, but also brick cladding reacts to minor millimeter movements with cracks.
  • Work should begin only after the project is completely ready, including the cost estimate. Saving time is illusory, and may be fraught with the fact that workers will be forced to stand idle due to the lack of drawings of the required unit or will be forced to work out connections according to their own understanding. An incorrectly determined volume of material or fasteners will force the contractor to run around the shops in search of what is missing. The worst situation is when the structure was made, but they did not know where to lay the inputs for communications. As a result, you have to break through finished walls or ceilings, which also entails certain costs.
  • When looking for a contractor, consider several proposals and compare prices. They shouldn’t be very different, and if someone offers services at a clearly reduced cost, find out what the savings are due to. Perhaps this is just a marketing ploy, and during construction there will be so many unforeseen expenses that the “profitable” commercial offer will still exceed the competitors’ estimate due to the rise in price.

Conclude a formal contract with the contractor, which includes schedules for work and payment. Do not be fooled by offers of large advance payments in order to speed up construction time, and finance only the actual amount of work completed. If something goes wrong, you can change the contractor at any stage, while it will be almost impossible to return the money paid in advance.

  • Start monitoring the construction from the moment the foundation is laid, and not when it’s already time for finishing. If you don’t understand this yourself, hire a technical supervision specialist who will take over the work at such important stages as:
  1. pit development;
  2. filling of soil cushions and degree of compaction;
  3. drainage device;
  4. laying out communication inputs;
  5. waterproofing;
  6. reinforcement work;
  7. concreting.

All this is hidden work, which is impossible to control after its completion. The money spent on technical supervision will pay off by saving you from many problems in the future.

Note: During the construction of walls, the masonry should be controlled both vertically and horizontally. Differences between gas blocks must be eliminated with a plane; this will relieve the walls from internal stresses, to which the blocks react with cracks. Also, eliminating irregularities minimizes glue consumption, which will result in direct savings.

Dependence of timing on materials and construction technology

The time frame for constructing a country house depends on the choice of material and construction method.

You can build a house from:

  • bricks;
  • aerated concrete;
  • foam concrete;
  • wood (timber, logs, carriage).

Each of these types of materials, due to its individual characteristics and characteristics, has its own safe construction period. Here one should not neglect building codes and technical standards.

In addition, each material requires a special approach. For example, laying brick is a more labor-intensive process than laying foam concrete blocks. And a wooden frame made from logs is built more slowly than a building made from timber.

The time frame for constructing a country house also depends on the method of constructing the box. In addition to the traditional method, boxes are used in country house construction:

  • panel;
  • frame;
  • modular;

When constructing panel boxes, finished products in the form of panels, made of composite wood panels with glue, are assembled into one whole. Then they strengthen it. Then ready-made partitions for the interior walls are also installed. They are also strengthened. All that remains is to build the top and cover it, and then carry out communications and do finishing work.

When a frame object is built, first a frame is created from boards and logs on a finished base. Rafters for the roof are being installed. Then this frame is sheathed with thermal insulation fragments. At the end the top is completed.

Frame and panel buildings are somewhat similar in their design. Both initially have a frame. However, other construction methods are coming onto the market. For example, a modular house assembled from wooden panels, insulated with composite compounds.

A frame or modular house can be built very quickly - literally in 2-3 months, if you do not do the basics. A building with a foundation, of course, takes longer to build.

Budget options for arranging a roof

The optimal solution is a gable roof without decorative elements and wide gables. The roof needs to be insulated - this will reduce heating costs in winter.

Available coating materials:

  1. Slate. The material is weatherproof and comfortable. Disadvantages: heavy weight, fragility, difficulty of installation, toxicity.
  2. Profiled sheeting. Economical solution with good performance characteristics. Disadvantages: the need to adhere to installation technology, careful sealing of joints, noise during rain, injuries during installation.

The prototype of corrugated cardboard and shingles is made of metal. According to its characteristics, the material is similar to corrugated sheets, but its purchase will cost more. Plus - the beautiful appearance of the finished roof.

There are many solutions on how to build a house yourself quickly and inexpensively. However, in any case, before starting housing construction, it is necessary to draw up a detailed plan, take into account the natural features of the region, calculate the consumption of materials and think about utilities. The project of a private house requires prior approval from the relevant authorities.

The roof is a complex structure. It includes rafters, sheathing, vapor barrier and waterproofing, insulation, roofing felt. To make a roof cheaper, you need to choose the right components of the roofing “pie”.

The easiest way to do without insulation and complex construction is to build a cold attic. The roof itself here consists of a rafter system, a simple lathe, a waterproof film and a roof - slate or metal tiles. The heating problem is solved by an air gap and floor insulation. The latter is much cheaper, since a bulk heat insulator, for example, expanded clay, can be laid on the floor.

Previously, a flat roof was considered expensive, since the simplest options, such as ondulin or slate, were not suitable for covering the floor. However, today laminated waterproofing materials and PVC membranes have appeared. The latter will be more expensive due to the need to hire a specialist - the seams must be welded during installation. But you can lay a roll roof yourself.

One way to reduce the cost of a conventional pitched roof is to choose inexpensive roofing felt. Much depends on weather conditions and the angle of inclination, as well as on the relationship between duration and price. Ondulin is very inexpensive, but is not durable and does not have high strength. The roof will have to be replaced no later than after 10 years. The corrugated sheet is much louder, but at the same time cool and transmits sound well. It will need insulation or a fairly spacious attic.

Ways to save

Current prices for building materials have led to the fact that even home renovation may soon acquire the status of “expensive”.
Building a real country house in these conditions seems like a hopeless task, but experts assure that it is still possible to build a country house for ordinary people. The first option, which will help you save money, concerns the characteristics of the selected project. Such a plan must be calculated rationally and practically. In this case, remember that it is important for architects to present you with a project, but not to reduce your costs in any way. In most cases, experts offer beautiful large buildings with bright facades, and many are fascinated by the design image. But our job is to build a cheaper house.

A high-quality and inexpensive house should not be like this:

  • Too small, first of all, the house must suit your needs.
  • Be uncomfortable.
  • A house doesn't have to be made from bad materials. For construction work, you can purchase inexpensive but high-quality materials.

Today there are many budget projects:

  • You can make a rectangular floor plan with a gable roof;
  • Build a one-story building without expensive ceilings, a large number of windows and stairs. This scheme will save a lot of money.
  • You can build a house without a basement or plinth; this standard saves on average about 30% of costs.
  • You can exclude the creation of unusual and original elements on the facade, for example, arches, bay windows, columns.
  • Decorate walls in the simplest ways.
  • The facade should be plastered with a cement-lime mixture.

Take the time to choose a project that will help you save on construction costs. This is not the only way to reduce costs.